Changes to new Calhoun High School approved
Mar 11, 2013 | 1051 views | 1 1 comments | 3 3 recommendations | email to a friend | print
As construction continues on the new Calhoun High School, school board members approved a change to the facility’s plans last week to include a swimming pool, or auditorium.

“The natatorium, which was included in the original design of the project as an add alternate, was a part of the education SPLOST approved by the voters in 2010,” said Don Hood, Calhoun City Schools’ Finance Director.

The school board approved an adjustment of about $4.8 million to the contracted guaranteed maximum price of the project, Hood said.

“This includes approximately $3.4 million for the construction of the natatorium,” he said. “Other major adjustments included constructing a covered walkway between buildings B and C, improving the asphalt track included in the base bid to include the installation of a polyurethane track surface and an improved drainage system; plus funding several smaller improvements.

“The adjustment also includes $475,000 for future contingencies,” he added. “These contingency funds will only be spent if necessary.”

Visit www.calhountimes.com for more news.
Comments
(1)
Comments-icon Post a Comment
Sneezlebug
|
March 11, 2013
I vote for the pool!!! The pool could be used by the local swim team as well as the high school students.
Postings are not edited and are the responsibility of the author. You agree not to post comments that are abusive, threatening or obscene. Postings may be removed at our discretion.