The system added a new music room with a classroom attached to it, modified three English classrooms into two science labs with a prep room and renovated two classrooms that used to be the choral room. The system also upgraded the heating and air condition system in the main building along with other minor repairs.
The entire project cost just over a million dollars, with $641,405 coming from the state and $365,867 from special-purpose, local option sales taxes (SPLOST).
For more on this report, see Mondays Rome News-Tribune